In force since 15 January 2026

Granny flats up to 70 m²: the plain-English guide

New Zealand now lets you build a simple, single-storey standalone granny flat of up to 70 m² without a building consent — if every condition is met. Here's what that means, and how we can help.

General guidance only. This page summarises information from the Ministry of Business, Innovation and Employment (MBIE) and the Government. It doesn't replace the Building Act, the Building Code, your council's requirements or professional advice — and the rules can change.

1. Check the basics

Answer these six questions for your section. They're the same checks we run with every customer.

  1. 1

    Is there an existing dwelling on the property?

    The granny flat has to sit alongside a main home.
  2. 2

    Is the new building 70 m² or less (internal floor area)?

    Every Hari design is 70 m² or under.
  3. 3

    Is the new building at least 2.0 m away from any other building?

    Including the main house.
  4. 4

    Is the roof no more than 4.0 m above the finished floor level?

    If this isn't possible, talk to us about options.
  5. 5

    Is the finished floor level no more than 1.0 m above the ground?

    If this isn't possible, we can discuss excavation options with you.
  6. 6

    Is the building at least 2.0 m from every boundary?

    Rural and lifestyle zones often need larger setbacks under the District Plan — we'll confirm this for your exact site.

0 of 6 answered — your result appears here.

2. The building consent exemption

Under the Building Act's granny flat exemption you can build a new, standalone, single-storey dwelling of up to 70 m² without a building consent, provided:

  • the design is simple and the finished building complies with the Building Code;
  • the building work is carried out or supervised by licensed building practitioners, with plumbing, drainlaying and electrical work done by authorised professionals;
  • you apply for and receive a project information memorandum (PIM) from your council before work starts; and
  • you notify the council when the build is complete, supplying documents such as final plans, records of work and certificates.

Councils can charge development contributions when they issue the PIM. They don't inspect or certify exempt work — so who builds it matters.

3. Resource consent

New national rules (the National Environmental Standards for detached minor residential units) make one detached granny flat of up to 70 m² per site a permitted activity in most residential, rural, mixed-use and Māori purpose zones — when conditions are met. These include having an existing main home on the site, keeping the unit at least 2 m from boundaries and the main house in residential zones, and total building coverage of no more than 50%. District and regional plan rules (for example natural hazards or infrastructure) still apply.

4. How Hari helps

All 13 of our designs are 70 m² or under. When you buy a Hari home we can manage the whole project — early research and council documentation, site works, foundations, water tanks, septic systems and solar — or supply a flatpack kitset for your licensed builder. We've already helped customers get underway using the new exemption pathway.

Get a free site-specific estimate Browse 70 m² & under homes

Official forms & sources

Call View homes

Your shortlist

Saved on this device. Send them to us in one enquiry and we'll come back with advice for each — customisation, site and delivery.

Your shortlist is empty.

Get the brochure

A few quick details and your download starts straight away. You'll only be asked once on this device.

Add budget or requirements (optional)

We only use your details to help with your project. Privacy